You assign (allocate) workers and assets to an order on the Assignar dashboard by dragging them from the Resources panel onto a shift on the Scheduler's Timeline. You can fill one shift or many shifts at once. You need the Orders user access module.
Your company can rename some words in Assignar, so you might see Role instead of Task, or Assignment instead of Allocation. The old help centre used "role" and "assignment".
Watch the video: https://fast.wistia.com/embed/medias/8qb30h1ke7
Video (3:00): Allocating workers and assets to shifts.
Assign a worker or asset to a shift
To assign a worker or asset to a shift on the Assignar dashboard:
Go to Work Planning > Scheduler and open the Timeline. The 1 Week range is the easiest to work in.
Expand the order, then click the shift you want to fill (a task on one day). The Resources panel opens on the right.
Open the Workers or Assets tab. Workers who suit the task and are free are listed under Recommended Workers; the rest are under Other Workers. See How do I find the best worker or asset for a shift in the Scheduler?.
Drag the worker or asset onto the shift.
The dashboard shows "Successfully allocated resources to task: …" and the worker's name appears on the shift card. The count on the shift card (for example 1 / 2) shows how many workers are allocated against how many the task needs.
Assign workers to many days at once
To assign the same worker or asset to several shifts at once on the Assignar dashboard, for example a whole week or a long order:
Click the first shift.
Hold Shift and click the last shift to select every shift in between, or hold Ctrl (Cmd on a Mac) and click shifts one by one.
Drag the worker or asset onto any of the selected shifts. They are added to all of them.
While shifts are selected, you can only drop resources on those shifts ("When you have shifts selected, you can only drop resources onto those selected shift(s)"). To fill a long order in one go, use a longer range such as 1 Month or 3 Months and select the shifts the same way. You can also hold Shift or Ctrl to select several workers in the panel and drag them together.
Assign an asset with its operator
When a task needs an asset and an operator on the Assignar dashboard, select the shift, drag the asset onto it, and then choose the operator. The panel header shows "Allocating Operator for …" while you pick the worker. See How do I find the best worker or asset for a shift in the Scheduler?.
Remove a worker or asset from a shift
To remove an allocation on the Assignar dashboard, hover over the worker's or asset's name on the shift card and click the bin icon, or click the pencil icon and choose Delete. To clear a whole shift, open the task's menu and click Remove resources. The dashboard asks "Do you want to remove all allocations from the task … for …?".
Other ways to allocate
You can also allocate on the Assignar dashboard from:
the Calendar view, by picking a task in the Orders panel and clicking a worker's day. See How do I use the Calendar view in the Scheduler?.
the Cards view, by dragging workers onto a day's order cards. See How do I use the Cards view in the Scheduler?.
a saved copy of a crew. See How do I copy a role's resources to the clipboard in the Scheduler?.
Why can't I assign a worker or asset?
These are the messages you might see when allocating on the Assignar dashboard, and what to do:
"Failed to allocate resources to task: …": the allocation wasn't saved. See the next section.
"You cannot allocate assets to a skill required task.": the task needs workers with a skill, not assets. Drag a worker instead.
"When you have shifts selected, you can only drop resources onto those selected shift(s)": drop onto a selected shift, or click elsewhere to clear the selection first.
"Clear previous selection?": you can only allocate one task at a time. Click Clear Previous to switch to the new task.
"Allocation is already on this shift.": that worker or asset is already on the shift.
"Cannot update past allocations.": shifts that have started can't be changed.
Nothing happens when you drag: your user has Read Only or no Orders module.
"Failed to allocate resources to task" or "Failed to assign resources to role"
The Assignar dashboard's Scheduler shows "Failed to allocate resources to task: General Workforce." (with your task's name) when it couldn't save an allocation you dropped onto a shift. The message uses your company's words, so it might read "Failed to assign resources to role: Supervisor." instead. The name at the end is the task you dropped onto, not the reason it failed. The worker or asset is taken off the shift again, because nothing was saved.
To fix it:
Click Refresh in the control bar, or reload the page, and try the allocation again.
Try one worker on one shift. If that works, allocate the rest in smaller groups.
Check whether it fails on other orders and for other schedulers. If allocating fails on every order, for everyone, the problem is probably on Assignar's side. See Is Assignar down? How do I check the service status?.
If it keeps failing, contact Assignar Support with the exact message, the order number, the task, the date, the worker or asset, and the time you tried.