How do I use order statuses in the Scheduler on the dashboard?

Every order on the Assignar dashboard has a status.

Every order on the Assignar dashboard has a status. The status shows what stage the job is at, and it decides whether workers can see their allocations in the Assignar mobile app. There are eight fixed statuses; they can't be renamed or added to. Dashboard users with the Orders user access module can change a status.

Your company can rename some words in Assignar, so you might see Job instead of Order.

The order statuses

The table below shows each order status on the Assignar dashboard, its colour in the Scheduler, and what it does.

Status

Colour

What it means

Pending

Orange

Still being planned. Workers don't see the order in the mobile app.

Confirmed

Green

Released to workers. Allocations show in the mobile app, and workers can be notified. The order's dates are locked.

In Progress

Blue

Released to workers, the same as Confirmed, and the order's dates can still be changed by dragging.

Declined

Red

Cancelled or lost. Workers don't see it.

Invoiced

Pink

Billed. Workers don't see it, and its dates are locked.

New

Teal

Workers don't see it. Used for orders created in the mobile app.

Completed

Grey

Finished. Workers don't see it.

Quote

Purple

A quoted job not yet won. Workers don't see it.

Confirmed and In Progress are the "released" statuses. Only orders in a released status appear on workers' My Day in the Assignar mobile app, and only those can send push notifications to workers. See How do I notify workers of their assignments from the Scheduler?.

Change an order's status in the Scheduler

To change an order's status in the Scheduler on the Assignar dashboard:

  1. On the Timeline, open the order's menu (⋮) next to its name.

  2. Open Order status and click the new status.

The dashboard shows "Order … status updated to …". You can also change the status in Order Status when you edit the order, then click Save Order or Save and Notify Workers.

The order menu on the Timeline with the status list open.

Set the status for new orders

New orders on the Assignar dashboard start with your company's default status. To change it, go to Settings > View/Edit Settings, open the Order settings tab and change Default Order Status.

Why can't my workers see their shifts?

If workers can't see their allocations in the Assignar mobile app, check the order's status on the dashboard. Workers only see allocations on orders that are Confirmed or In Progress, and they don't see declined allocations, archived orders, or orders on archived projects. Change the status to Confirmed to release the order. See also Why can't I see my assignment on the mobile app?.

Why can't I drag a Confirmed order on the Timeline?

The dates of orders with a Confirmed or Invoiced status are locked on the Assignar dashboard: you can't drag them on the Timeline, Move orders won't select them, and the date fields in the order form are greyed out. To change the dates, set the status to In Progress or Pending first, change the dates, then set it back. See How do I change an order's dates and duration in the Scheduler?.