You can move up to 40 orders earlier or later by the same number of days in one go on the Assignar dashboard, using Move orders on the Scheduler Timeline, for example when a whole week of work is rained off. You need the Orders user access module.
Your company can rename some words in Assignar, so you might see Job instead of Order.
Watch the video: https://www.loom.com/share/f491b5774e3f4bf78c32d4e03810a291
Video (1:01): Moving several orders at once with Move orders.
Before you start
You can select at most 40 orders at once.
Orders with a Confirmed or Invoiced status can't be selected. Change their status first if they must move. See What does each order status mean on the dashboard?.
Submitted timesheets on the moved orders are kept on their original dates as loose timesheets (no longer linked to an allocation).
Move several orders
To move several orders together on the Assignar dashboard:
Go to Work Planning > Scheduler and open the Timeline.
Turn on Move orders in the control bar ("Select multiple orders to move their dates together"). A tick box appears beside each order.
Tick the orders to move. The bar shows how many are selected ("… selected").
Click Move orders.
In Move … selected orders, choose the Direction: Later → or Earlier ←.
Enter the Number of days.
Optional: tick Schedule on non-working days to move by calendar days ("Move by actual calendar days, including non-working days."). Otherwise orders move by working days, so shifts don't land on non-working days.
Click Move.
The dashboard shows "Moved … orders." If some couldn't move, it adds "… skipped.", or "No orders were moved. … skipped." if none could.
Why can't I select an order?
On the Assignar dashboard, an order's tick box is unavailable in Move orders when the order is Confirmed or Invoiced. If you try to select more than 40, the dashboard says "You can move up to 40 orders at once. Deselect some to continue." Move orders isn't shown to users with Read Only.