The Projects Timeline and Resources Timeline on the Assignar dashboard are older Gantt charts of your orders. The Projects Timeline shows orders and their tasks over time. The Resources Timeline shows each worker or asset with their allocations, and lets you add, swap or remove allocations. Users with the Orders access module can use both. Most scheduling is now done in the Scheduler; see Getting started with the Scheduler on the dashboard.
Your company can rename some words in Assignar, so you might see Role instead of Task, or Job instead of Order, and the Projects Timeline is named after your word for projects. An allocation is a worker or asset assigned to a task on a date (the old help centre called this an assignment).
Open the Projects Timeline on the dashboard
To view orders and tasks on the Projects Timeline on the Assignar dashboard:
In the left menu, go to Work Planning > Projects Timeline.
In the Options panel, set the filters you need:
Scale: hour, day, week or month.
Date range: pick the start and end dates from the calendar. It starts on the start of this week and ends two weeks from today.
Client, Project and Task: choose one, or leave -- All --.
Order Owner and Order Tags.
Click Load Timeline. The page shows "Loading timeline view..." and then the chart.
Each bar shows a task's dates, with Start and End columns on the left. The Projects Timeline is view only: you can't drag bars to change orders. To change an order, use the Scheduler.
Open the Resources Timeline on the dashboard
To view workers or assets and their allocations on the Resources Timeline on the Assignar dashboard:
In the left menu, go to Work Planning > Resources Timeline.
In the Options panel, choose View By: Assets or Workers. Your company's settings decide which one comes first.
Set the other options you need:
Worker Tags or Asset Tags: show only resources with these tags.
Scale: hour, day, week or month. Click Day view to zoom in on a single day.
Sort: name, from, to, client or project.
Filter Rows: type part of a name to show only matching rows.
Date range: choose a preset such as Last and next 7 days (the default), Next 7 days or Next 30 days, or pick dates.
Client, Project, Task, Order Owner and Order Tags.
Click Load Timeline.
Each row is a worker or asset, and each bar is one of their allocations. Click Export to Excel to download what the timeline shows.
Save your timeline filters on the dashboard
To keep your filters on the Projects Timeline or Resources Timeline on the Assignar dashboard, set them and click the green pin button (Save this search). The timeline opens with those filters next time. To go back to the defaults, click the red x button (Clear saved search).
Refresh the Resources Timeline automatically on the dashboard
To keep the Resources Timeline on the Assignar dashboard up to date while you watch it, tick Enable auto-refresh under the Options panel. The timeline reloads every 10 minutes and shows "Refreshing in" with a countdown. Untick it to stop.
Add an allocation from the Resources Timeline on the dashboard
To allocate a worker or asset to an order from the Resources Timeline on the Assignar dashboard:
Load the timeline with View By set to Workers or Assets.
On the worker's or asset's row, click and drag across the day you want. A new bar called New appears and the Add new allocation window opens with the date.
Click View existing orders. The window lists the order tasks on that day as "[order ID] - [task] - [client], [project]". If there are none, it says "No tasks on this day." for a worker, or that the asset cannot be added to any order tasks on this day.
Click the order and task you want.
On a wet hire order, choose who goes with the allocation:
When you started from a worker, choose an asset under Select an asset.
When you started from an asset, tick the workers under Select workers, and any attachments under Select attachments.
Click Save. The window asks "Would you like to save the following allocation?" and shows the worker, asset, task and order.
Click Save selection.
To create a new order for that day instead, click Create new order in step 3. To close without saving, click Cancel: the New bar disappears.
Change or remove an allocation from the Resources Timeline on the dashboard
To change an allocation on the Resources Timeline on the Assignar dashboard, click its bar. A window shows the order, task, client, project, date and times, with these buttons:
Remove Allocation: the dashboard asks "Are you sure you want to delete [name] on [date]?". Click OK to remove it.
Swap Worker (Workers view only): pick another worker under Select worker to take over the allocation.
Order Summary: opens a summary of the order.
View Allocation: opens the order's allocations in a new tab.
View Notifications: opens the order's notifications in a new tab.
See a worker's or asset's details from the Resources Timeline on the dashboard
To see details from the Resources Timeline on the Assignar dashboard, click the name at the start of a row:
For a worker: Send SMS (needs the SMS access module and a phone number), View Profile and View Qualifications.
For an asset: View Detail.
Why is the timeline empty or not loading on the dashboard?
These are the common reasons the Projects Timeline or Resources Timeline on the Assignar dashboard shows nothing:
"Please select your criteria and click the Load Timeline button": the timeline doesn't load until you click Load Timeline.
"No results": nothing matches the filters. Widen the Date range, set Client, Project and Task back to -- All --, and clear the tags.
A saved search is hiding orders. Click Clear saved search (the red x) and load again.
"This export isn't available at this time." or "An error occurred, please try again later.": the Excel export failed. Try again, or use a shorter date range.
The order is archived. Archived orders don't appear on the timelines.
If the timeline still won't load, refresh the page or try another web browser. If it keeps failing, contact Assignar support with a screenshot.