How do I record progress in the Site Diary on the mobile app?

Supervisors can record how much work was done each day in the Site Diary on the Assignar mobile app, for example metres of pipe laid or cubic metres excavated.

Supervisors can record how much work was done each day in the Site Diary on the Assignar mobile app, for example metres of pipe laid or cubic metres excavated. Progress is recorded against the order's activities and adds up to a running total against the budget, which the office sees on the Assignar dashboard.

Your company can rename some words in Assignar, so you might see different words for Activity, Order or Site Diary.

Before you start

  • Progress tracking must be switched on for your company. If the Site Diary has no Progress card, ask your company's admin.

  • Only activities with a unit of measure (such as m, m³ or each) can be tracked. Activities and units are set up on the Assignar dashboard.

  • The Site Diary must be for an order. Unscheduled Site Diaries without an order have no Progress card.

Record progress in the Site Diary on the mobile app

To record progress in the Site Diary on the Assignar mobile app:

  1. Open the Site Diary from your shift card on My Day.

  2. Open the Progress card ("How much progress did you make?") and tap +.

  3. Pick the activities you worked on. Recommended lists the order's activities that have a unit of measure and aren't tracked yet today. Tap Show Other Activities for other activities with a unit of measure. Tap Next.

  4. For each activity, on Add Progress:

    • Choose Unit to enter an amount, or % to enter a percentage of the budget (the app converts it to units)

    • Enter the Quantity

    • Add Comments (up to 1,000 characters) and photos if you like.

  5. Check the running total, for example: "Total to date: 120/400 m". If the activity has no budget, it shows "Total to date: 120 m".

  6. Tap Save. The app shows "Progress updated".

Change or delete progress on the mobile app

To change progress you've recorded, tap the activity on the Progress card to open Edit Progress, change it and tap Save. To remove it, tap Delete and confirm Confirm Delete. If saving fails, the app shows "Quantities failed to save". The quantity must be a number of 0 or more.

The older Work Completed card

Some companies see a Work Completed card instead of Progress in the Site Diary on the Assignar mobile app ("Report work completed for the day"). This appears when progress tracking isn't switched on, and the order has budgeted quantities. Enter the amount or percentage completed today for each item ("Add amount for today" or "Add percentage for today"). The app shows "Quantities changes saved".

Why can't I record progress in the Site Diary?

  • No Progress card. Progress tracking isn't switched on for your company, or the Site Diary has no order.

  • An activity isn't in the list. It has no unit of measure, or it's already tracked today (tap it on the card to edit it instead).