Push Shifts Forward

  • Updated

If an order is delayed due to weather, material shortages, scope changes or any sort of dependency delay, you can easily push out all shifts on the order from the Timeline view of the Scheduler. On the day of the order that needs to be pushed forward, click the ellipses at the top of the shift and select "Push Shifts Forward".

Screenshot 2025-04-29 at 1.19.44 PM.png

You can then specify how many days to push the order and if shifts should push into non-working days.

Screenshot 2025-04-29 at 1.22.21 PM.png

Notes:

  • If the shift has already started or is in the past, you cannot push it forward
  • Pushing a shift forward extends the order end date